Sheffield City Council
Project status
Wave 1: First schools opening January 2009
Wave 4: Project started February 2007; next stage Financial Close
Sheffield's Wave 1 project is refurbishing and rebuilding nine mainstream secondary schools and five secondary schools for students with special educational needs. Newfield and Silverdale are due to open in January 2009.
Sheffield also has a repeat project allocated to Wave 4 of BSF, in which 12 schools will be refurbished or rebuilt, and a further 10 schools will receive ICT investment but no construction work.
Sheffield's LEP Partners
| Bidder | Paradigm |
| LEP Equity Provider | Taylor Woodrow, HSBC Infrastructure Management Ltd |
| Construction | Taylor Woodrow, Henry Boot |
| Design | HLM Architects |
| Hard FM | Taylor Woodrow FM |
| Soft FM | Taylor Woodrow FM |
| ICT | Civica and Broadband Learning |
| Partnering Services | Place Group |
| Funders | RBC/SMBC |
Wave 1
Funding:
| Conventional Funding | £70.3m |
| PFI Credits | £88.9m |
(Includes ICT. Funding allocations are indicative and are likely to change.)
Wave 4
Funding:
| Conventional Funding | £207.8m |
| PFI Credits | £60m |
(Includes ICT. Funding allocations are indicative and are likely to change.)